Active Water Treatment Plant & Turnbull Anchor – Fording River Operations

  • Client Name: Teck
  • Project Name: Active Water Treatment Plant & Turnbull Anchor – Fording River Operations
  • Location: Elkford, BC
  • Sector: Mining

Duration: 33 months

Crew size: 50

Highlights:

  • 11,000m³ concrete poured
  • 30+ large tank bases with on-site batch plant
  • Cellular concrete pipe zone fill
  • Sandblast & epoxy coating on tank bases
  • 700m2 of masonry block walls (300mm wide)
  • Supply & install of 1m diameter embedded pipe sleeves
  • Monitored heat of hydration using digital thermal couplers
  • Mass concrete pour including internal thermal coupler installation and heat of hydration monitoring
  • Large 1m x 3m steel pipe embeds installed into mass concrete pour
  • Project delivery on schedule and budget during adverse winter weather conditions