Operations Expansion – Gibraltar Mine
Duration: 19 months
Crew size: 80
Highlights
- 37,000m³ of concrete poured
- Construction of foundations for concentrator & moly building, ball & SAG mill, flotation cell, conveyor & transfer/take up towers, reclaim tunnel, tailings sump box, grinding operations floors, in-pit & primary crushers
- Excavation, backfill, demolition, formwork, rebar, embedded steel & anchor bolt installation, and concrete placement